UT3 Updated

Welcome to interactive presentation, created with Publuu. Enjoy the reading!

24

Within the space of a couple of

hours after the cable was laid,

ROV images showed sand being

ejected out from under that

cable. The result was that the

cable rapidly became self-

embedded into the seabed and

thus became profoundly stable.

At adjacent locations on those

cables, where they crossed

existing assets (pipelines, cables)

buried in the seabed, they were

required to install hollow sleeves

on the outside of the cable to

guarantee separation with the

existing assets.

“Those hollow sleeves were

actually free to roll around the

cable which effectively meant

that the CSS, (crossing

separation system) was free to

roll backwards and forwards. This

made it profoundly and

fundamentally unstable.

Using our knowledge of cable

scour meant the crossings could

be installed with confidence,

knowing they would self embed.

“By analysing videos taken on

site, it is possible to observe the

rate at which sand is being

ejected out. This meant the

scouring was occurring

underneath that cable as

predicted.

“Again, within the space of 6–

12hrs, that system self-

embedded into the seabed and

became fundamentally stable

and did not move laterally.”

“When the installation

contractor returned to undertake

permanent stabilisation works of

the crossings, they found that the

cables and CSS had Indeed self-

embedded Into the seabed and

remained stable.

Elsewhere in Scotland, the group

have been looking at the power

cables that connect the UK's first

tidal stream energy project to the

grid - the MayGen tidal stream

project owned by SAE

Renewables.

“It is clearly possible to see the

extent to which these bare cables

- with no added external

protection applied to them, have

naturally found nooks and

crannies in the seabed into which

they have become wedged and

thus become self-stable.

“The seabed is characterised by

hard rocks and thus, the cables

could not buried. Instead, they

have been placed on the bare

rock surface. The rock was not flat

and on a smaller scale, had cracks

and boulders distributed across

the surface.

“Conventional wisdom would

suggest that the cables would be

free to slide across the surface

but upon investigation, the cables

embedded themselves between

the boulders and undulations and

ultimately self-stablised on the

seabed.

“It is critical to understand and to

learn by looking carefully at what

is happening in the ocean,

understanding the relevant

physics and then tailoring the

engineering solutions to suit.

“When applying the relevant

physics to the design, we

wind up being able to show

some rather extraordinary

outcomes that these cables

are actually self-stable.

“This is not what you would

expect if you just inherited

the oil and gas design

methods, and based on the

different sets of ROV footage

we've actually got proof when

we've taken the design

methods that were inspired

by watching the Maygen

cables and we've been able

to apply them to now two

offshore wind farms off the

Atlantic coast of Europe that

have been developed on

entirely rocky seabeds.

“It was a career highlight to

stand on the cliffs at Le

Croisic near St Nazaire and

look out towards France's first

offshore windfarm a few

weeks after it was

commissioned.

This project demonstrates

what we are advocating - that

the offshore renewables

industry actually needs new

design guidance that is

actually fit for purpose for

subsea cables.

They need to be based on a

new mindset a new paradigm

for how we go about setting

the target risk and the target

reliability for subsea cables so

that we one lower the cost

but two improve the

performance of cables.

NEWS

Made with Publuu - flipbook maker